Week 18 — Jan 4-10, 2026

Overview

Revamp strict timeline for mechanical and electrical systems and began fabrication of core components.

Individual Updates

Austin

  • Researched stepper motor suppliers and control archiitecture
  • Specced out stepper motor sizes for elbow and turret
  • Specced out rotary encoders for closed loop stepper motor control

Grace

  • Purchased materials for linear rail launcher
  • Designing 3D printed prototype capstan reducer for elbow & turret, to prepare for final CNC'd parts
  • Planned fabrication timeline for all mechanical components

Kevin

  • Developed BLDC motor closed loop control
  • Sensorless zeroing of motors
  • Implemented CAN comms via ROS2 network

Vincent

  • Start schematic and PCB layout for Power Distrubution Board
  • Look into power regulation for all sub-systems
  • Finalize wire harnessing for power and communination